Nakusp Hot Sprints replacement work bee:
- Tuesday Sept 12 – stage timber and build loads using nets and straps. Complete slinging from CMHA upper helipad to crossing site. Lower timbers, generator and tools through trees to drop site as close to crossing as possible. Begin removal of existing rotted cedar rough cut bridge.
- Thursday & Friday (Sept 14 & 15) – complete site prep, hand carry timbers from drop site to crossing, build bridge! Hike out tools, generator and sling net at end of job.